2023 Capital Improvement Projects

North Bird Street Reconstruction Project

LIMITS: 151 Bridge to North City Limits approx. 200 feet north of Stonehaven Drive

WHEN: The project window is tentatively between April 24 and August 28. 

SCOPE OF PROJECT: The project will include new water main and services from the bridge to Tower Drive, new storm sewer from detention basin to Schumann Street, new curb & gutter, crushed aggregate base course, bituminous concrete pavement, and new multi-purpose path on the west side. 

The project will eliminate the existing medians but will include smaller medians at the intersections to provide a refuge area for pedestrian. There will be some street closures associated with the project and will be phased to avoid school traffic and to expedite access to local businesses. 

PROJECT CONTACT: Clint Christenson, P.E. 608-825-1170

Commercial Avenue Reconstruction Project

LIMITS: S Bird Street to Kroncke Drive, also resurfacing S Bird Street from Lothe Street to concrete pavement north of Commercial Ave/south of W Main Street. 

WHEN: The project window is tentatively between April 24 and August 28 with an 80 calendar day construction period once construction commences. 

SCOPE OF PROJECT: This project will include new water main and services from the new curb & gutter, storm sewer re-alignment, crushed aggregate case course, sanitary sewer manhole replacements, bituminous concrete pavement, and new multi-purpose path on the west side. 

The project will be constructed under local traffic only - no through traffic. The multi-use path on the south side of Commercial Ave will be replaced in a separate project in conjunction with this project. 

PROJECT CONTACT: Clint Christenson, P.E. 608-825-1170

O'Keeffe Avenue - Linnerud Drive Pavement Rehabilitation Project

LIMITS: O'Keeffe Avenue from Sunfield Street south to the first roundabout. Linnerud Drive from O'Keeffe Avenue to Clarmar Drive. 

WHEN: The project window is tentatively scheduled between June 12 and August 28. 

SCOPE OF PROJECT: This project will include spot repairs to the existing curb, gutter, and sidewalk, extend extend the existing multi-purpose path from Hunter's Trail north to Linnerud Drive on the east side of O'Keeffe Avenue. The project will include replacement of existing asphalt pavement. 

The project will be constructed under local traffic. 

PROJECT CONTACT: Michael Campos, P.E. 608-825-1170

Clarmar Drive Sidewalk Extension Project

LIMITS: Approximately 130 feet south of Echo Drive to Linnerud Drive on the east side of Clarmar Drive. This is to eliminate the gap in the sidewalk network along Clarmar Drive. 

WHEN: The project window is tentatively between June 12 to August 28. 

SCOPE OF PROJECT: Install a 5-foot wide sidewalk on the east side of Clarmar Drive to eliminate gap in sidewalk network. 

The project will be constructed under local traffic. 

PROJECT CONTACT: Jeffrey Luther 608-825-1170

Grove Street - E Main Street Multi-Use Path Reconstruction

LIMITS: Robin Drive to East Main Street on east side of Grove Street. Grove Street to Wood Violet Lane on the south side of E Main Street. 

WHEN: The project window is tentatively between June 12 to September 29. 

SCOPE OF PROJECT: Reconstruction of existing multi-use paths along east side of Grove Street and south side of E Main Street. 

The project will be constructed under local traffic. 

PROJECT CONTACT: Andrew Minga 608-825-1170